We are using a three-phased approach that grows cloud skills and organizational maturity during the process of moving to the Cloud, ultimately positioning us to take full advance of Cloud benefits.
As an important first step, HUIT is immediately discontinuing all on-premises provisioning at the 60 Oxford Street data center, and implementing a ”Cloud first” policy that all new applications should be created in the Cloud.
|
Phase One: Support Migrations and disaster recoveryJune 2014-April 2017
Resources: Forming and storming Cloud team Migrations:
Operations:
Cloud Skills and Operational Maturity: Basic
|
|
Phase Two: Deliver Minimum Viable ProductMay 2017-December 2018
Resources:
Migrations: 100% of HUIT apps to be migrated or retired by December 2018 Operations:
Cloud Skills and Operational Maturity: Expanded
|
|
Phase Three: Automate and OptimizeJanuary 2019 - June 2020
Resources: Performing Cloud team Applications:
Operations:
Cloud Skills and Operational Maturity: More Advanced |