Progress Statistics
Our journey to the Cloud has three phases. We are currently in phase two: Deliver Minimum Viable Product (MVP). During phase two, we are both migrating servers and applications to the Cloud, and removing the physical infrastructure from our 60 Oxford Street data center. |
We are 100% complete migrating to the Cloud.
Beween FY14 and September 2018, we migrated 556 servers, representing 570 applications.
Items Removed
-
There are 236 assets left to remove from the 60 Oxford Street data center
- Decommission 128 servers
- Relocate 108 servers